Late last month, the United States District Court for the District of Idaho denied preliminary injunctive relief in an Endangered Species Act case against the Fish and Wildlife Service (FWS) and Forest Service, even though it found that "the required rational connection was not made in the [section] 7(d) determination," because declarations submitted to the … Continue Reading
In a published opinion (pdf) affirming the denial of preliminary injunctive relief, the U.S. Court of Appeals for the Ninth Circuit held that "there is no statutory mandate to consider cumulative effects during informal consultation." Conservation Congress v. U.S. Forest Serv., No. 12-16452 (June 13, 2012). In order to address issues in the Shasta-Trinity National … Continue Reading
On October 22, 2012, the Ninth Circuit Court of Appeals held that the U.S. Fish and Wildlife Service (Service) abused its discretion when it issued a biological opinion (BiOp) and incidental take statement for the Ruby Pipeline Project, and ordered the Service to prepare a revised BiOp. Center for Biological Diversity v. U.S. Bureau of Land … Continue Reading
On August 13, 2012, the United States Court of Appeals for the Ninth Circuit laid to rest litigation that threatened to profoundly affect water and power supplies for 25 million people throughout the arid Southwest. In Grand Canyon Trust v. U.S. Bureau of Reclamation (pdf), the Ninth Circuit held that the U.S. Bureau of Reclamation (Reclamation) is not required to consult … Continue Reading
On June 1, 2012, a sharply divided Ninth Circuit sitting en banc filed an opinion in Karuk Tribe of California v. U.S. Forest Service, No. 05-16801 (June 1, 2012) (pdf) holding that U.S. Forest Service "approvals" of notices of intent (NOIs) to undertake suction dredge mining are discretionary agency actions that may affect listed coho salmon designated critical habitat in the Klamath … Continue Reading
In a recent decision out of Oregon, a United States District Court found that plaintiffs do not need to prove a likelihood of future take to prevail on a Section 9 claim. Stout v. U.S. Forest Service, ECF No. 112 (D. Or. April 24, 2012). Plaintiffs, ranchers who had been partially enjoined from grazing on certain banks because of potential impacts … Continue Reading
On March 8, 2012, the U.S. District Court for the Eastern District of California entered judgment in Coalition for a Sustainable Delta and Kern County Water Agency v. Federal Emergency Management Agency, et al., No 1:09-cv-02024 (E.D. Cal.) based on a settlement agreement in which FEMA agreed to request consultation with the National Marine Fisheries … Continue Reading
On October 17, 2011, U.S. District Judge Sullivan issued two opinions in the Polar Bear litigation previously blogged about here. In the first opinion (pdf), Judge Sullivan held that the U.S. Fish & Wildlife Service violated the National Environmental Policy Act (NEPA) by issuing a rule under section 4(d) of the Endangered Species Act (ESA) regarding take … Continue Reading
On August 19, 2011, the U.S. District Court for the Eastern District of California denied in part and granted in part FEMA’s motion for partial summary judgment (PDF) in the latest in a series of lawsuits filed against FEMA for failing to consult under Section 7 of the Endangered Species Act (ESA) regarding the impacts of … Continue Reading